COA Opinion: Drilling test well constitutes "actual physical improvement" under Construction Lien Act, and contract determines amount of the lien

In Michigan Pipe & Valve-Lansing, Inc. v. Hebeler Enterprises, Inc., No. 294530, the Michigan Court of Appeals held that a test well drilled on a development property constituted an "actual physical improvement" under the Construction Lien Act, and that the lien amount includes all interest charges contemplated by the underlying construction contract.

Defendant Windy Pines View, LLC ("Windy Pines") intended to develop a residential subdivision on its property. To secure project financing, Windy Pines granted a mortgage to Defendant Firstbank-St. Johns, which was subsequently recorded on February 10, 2005. Two days before the mortgage wsa recorded, a contractor drilled a well on the property in order to obtain a water sample. The well was subsequently capped after Windy Pines decided to rely on the Township for its water supply. In 2007, the property owner contracted with Defendant Hebeler Enterprises, Inc. ("Hebeler") to build infratructure and roads for the proposed subdivision. Hebeler purchased materials from Defendant Grand River Infrastructure, Inc. ("GRI") and Plaintiff Michigan Pipe & Valve ("MPI") to complete the project. Although Windy Pines paid in full for Hebeler's work, Hebeler failed to pay both GRI and MPI, which filed claims of lien in 2008. GRI and MPI foreclosed on the liens, claiming priority over the mortgage under the Construction Lien Act.

The trial court held that the liens indeed had priority over the mortgage, reasoning that the well was an "actual physical improvement" under MCL 570.1103(1), and that the liens had priority over all other interests in the property, including the mortgage, under MCL 570.1119(3). The trial court awarded GRI the value of its lien, plus "sums representing the time-price differential charges of 1.5 percent per month" as provided in the contract between GRI and Hebeler. The trial court similarly awarded MPV the value of its lien, but held that it was not entitled to the 1.5 percent per month "service charge," because it did not constitute "interest" as defined in the Construction Lien Act.

The Court of Appeals affirmed in part and reversed in part. The Court affirmed that the well was indeed an "actual physical improvement," because the well was a readily visible, physical, and permanent change to the property, and that due to its permanency, the Construction Lien Act's exception for "labor which is provided in preparation for [] change or alteration" to the property was not applicable. The Court reversed the trial court's determination that MPV's "service charge" was not included in its lien, however. The Court reasoned that the service charge was "an amount owed in return for the privilege of purchasing goods . . . with credit," and therefore was an "interest" charge that was properly included in MPV's lien under the Construction Lien Act.

NOTICE. Although we would like to hear from you, we cannot represent you until we know that doing so will not create a conflict of interest. Also, we cannot treat unsolicited information as confidential. Accordingly, please do not send us any information about any matter that may involve you until you receive a written statement from us that we represent you.

By clicking the ‘ACCEPT’ button, you agree that we may review any information you transmit to us. You recognize that our review of your information, even if you submitted it in a good faith effort to retain us, and even if you consider it confidential, does not preclude us from representing another client directly adverse to you, even in a matter where that information could and will be used against you.

Please click the ‘ACCEPT’ button if you understand and accept the foregoing statement and wish to proceed.

ACCEPTCANCEL

Text

+ -

Reset